Chaussée de Roodebeek 61, Woluwe-Saint-Lambert: operation of installations. Case octroyé, lodged on 9 April 2020. The decision was notified on 7 June 2021, 424 days after lodging.
Exploitation d'une menuiserie| Permit type | Prolongation de PE | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 9 April 2020 | date the file was received |
| Decision notified | 7 June 2021 | 424 days |
| Works started | 26 January 2022 | |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 4 m | Regularisation | régulariser un logement en intérieur d’îlot | 2026 |
| 16 m | Split into dwellings | régulariser la division d'une maison unifamiliale en 2 appartements et le changement des châssis | 2025 |
| 33 m | Roof | construire deux lucarnes et isoler la toiture (sarking) de la maison unifamiliale | 2022 |
| 48 m | New construction | construire un immeuble mixte (commerce et logements) sur le terrain | 2022 |
| 61 m | Extension or raising | régulariser l'aménagement d'un box de garage, de deux emplacements de parking ainsi que la création d'une cave à l'arriè | 2022 |
Other nearby cases : 18/PFD/1962898, 18/PU/1954105, 18/PFD/1893257, 18/AA/1988032, 18/PU/1825980, 18/PFD/1914155, 18/AA/1842895, 18/PU/2040720, 18/AA/1838994, 18/PU/2025924, 18/PU/1977421, 18/PU/1891933, 18/PU/1848963, 18/AA/2019693, 18/PU/1985766, 18/PU/1836713, 18/PU/1903341, 18/PU/1954385, 18/PU/1863624, 18/PU/1965443, 18/PU/1903325, 18/PU/1907465, 18/PU/1969526, 18/PU/1810506, 18/PU/1969447