Chaussée de Roodebeek 61

Woluwe-Saint-Lambert · 18/IPEPLP/1747166 · Prolongation de PE

Chaussée de Roodebeek 61, Woluwe-Saint-Lambert: operation of installations. Case octroyé, lodged on 9 April 2020. The decision was notified on 7 June 2021, 424 days after lodging.

Exploitation d'une menuiserie
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typeProlongation de PE
StatusOctroyé
Lodged on9 April 2020date the file was received
Decision notified7 June 2021424 days
Works started26 January 2022
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Granted
  5. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
4 mRegularisationrégulariser un logement en intérieur d’îlot2026
16 mSplit into dwellingsrégulariser la division d'une maison unifamiliale en 2 appartements et le changement des châssis2025
33 mRoofconstruire deux lucarnes et isoler la toiture (sarking) de la maison unifamiliale2022
48 mNew constructionconstruire un immeuble mixte (commerce et logements) sur le terrain2022
61 mExtension or raisingrégulariser l'aménagement d'un box de garage, de deux emplacements de parking ainsi que la création d'une cave à l'arriè2022

Other nearby cases : 18/PFD/1962898, 18/PU/1954105, 18/PFD/1893257, 18/AA/1988032, 18/PU/1825980, 18/PFD/1914155, 18/AA/1842895, 18/PU/2040720, 18/AA/1838994, 18/PU/2025924, 18/PU/1977421, 18/PU/1891933, 18/PU/1848963, 18/AA/2019693, 18/PU/1985766, 18/PU/1836713, 18/PU/1903341, 18/PU/1954385, 18/PU/1863624, 18/PU/1965443, 18/PU/1903325, 18/PU/1907465, 18/PU/1969526, 18/PU/1810506, 18/PU/1969447

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)