Avenue Konrad Adenauer 3

Woluwe-Saint-Lambert · 18/IPEPLP/1955620 · Prolongation de PE

Avenue Konrad Adenauer 3, Woluwe-Saint-Lambert: operation of installations. Case octroyé, lodged on 30 August 2024. The decision was notified on 12 August 2025, 347 days after lodging.

Exploitation d'une haute école
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typeProlongation de PE
StatusOctroyé
Lodged on30 August 2024date the file was received
Decision notified12 August 2025347 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
63 mMerger of dwellingsrégulariser la modification de deux studios (+ mezzanine) en un appartement duplex aux deuxième et troisième étages de l2023
126 mTree fellingabattre quatorze arbres dans le jardin de l'immeuble2022
141 mExtension or raisingEtendre et rénover un centre de jour et d'hébergement pour enfants polyhandicapés et réaménager les abords2023
158 mPublic spaceMaillage bleu UCLouvain - tronçon final : - moine à batardeau (déplacement au Nord de la nouvelle mare - chantier IPI) 2024
170 mOtherInstaller des cartels - parcours culturel ALlons MArcher !2025

Other nearby cases : 18/PU/1866771, 18/PFD/1966389, 18/PU/1967456, 18/PU/1930406, 18/PU/1930503, 18/PU/1945429, 18/PU/1821447, 18/GOU_PU/1951592, 18/PFD/1836021, 18/AA/1823763, 18/PU/1853764, 18/PU/1837455, 18/PU/1837211, 18/PU/1987709

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)