Withdrawn
Chemin de la Crète
Woluwe-Saint-Lambert · 18/IPEPLP/443518 · Prolongation de PE
Chemin de la Crète, Woluwe-Saint-Lambert: operation of installations. Case annulé, lodged on 7 January 2004. The decision was notified on 27 July 2004, 202 days after lodging.
installation de banalisation, stockage et broyage déchets spécifiques d'activités de soins| Permit type | Prolongation de PE | |
|---|---|---|
| Status | Annulé | |
| Lodged on | 7 January 2004 | date the file was received |
| Decision notified | 27 July 2004 | 202 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Decision notified · Withdrawn
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)