Boulevard de la Woluwe 64

Woluwe-Saint-Lambert · 18/IPEPLP/460281 · Prolongation de PE

Boulevard de la Woluwe 64, Woluwe-Saint-Lambert: operation of installations. Case annulé, lodged on 23 January 2012. The decision was notified on 27 January 2012, 4 days after lodging.

Dossier classe 2 à traiter par la commune
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typeProlongation de PE
StatusAnnulé
Lodged on23 January 2012date the file was received
Decision notified27 January 20124 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Decision notified · Withdrawn

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mSigns and advertisingCLASSE SANS SUITE placer un totem dans la zone de recul de l'immeuble2024
0 mSigns and advertisingplacer un totem en zone de recul de l'immeuble2025
44 mPublic spaceRéaménager le parc Saint-Lambert.2022
49 mPublic spaceRéaménager le parc Saint Lambert avec une installation artistique qui soulignera le caractère naturel du site.2024
52 mChange of useModifier le permis 18/PFD/1909197, changer la destination des surfaces commerciales au rez-de-chaussée en équipement d’i2026

Other nearby cases : 18/PFD/1909197, 18/PFD/2009080, 18/PU/1997195, 18/PU/2001774, 18/PU/1912885, 18/PU/2035016, 18/PU/1825288, 18/PU/1825278, 18/PU/1966206, 18/PU/1989687, 18/PU/1892347, 18/PU/1902328, 18/PU/2018121, 18/PU/2026548, 18/PU/1973486, 18/PU/2044356, 18/PU/2011270, 18/PFU/2022965, 18/PFU/1998458, 18/PFU/1859699, 18/PFU/1914471, 18/PFU/1952749, 18/PFU/1991105, 18/PFU/1830434, 18/PFD/2032394