Avenue Albert-Elisabeth 32
Woluwe-Saint-Lambert · 18/IPETMP/1694640 · Permis d'environnement temporaire
Avenue Albert-Elisabeth 32, Woluwe-Saint-Lambert: operation of installations. Case annulé, lodged on 20 November 2018. The decision was notified on 28 February 2019, 100 days after lodging.
Exploitation d'un chantier amiante| Permit type | Permis d'environnement temporaire | |
|---|---|---|
| Status | Annulé | |
| Lodged on | 20 November 2018 | date the file was received |
| Decision notified | 28 February 2019 | 100 days |
| Works started | 25 March 2019 | |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Withdrawn
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Tree felling | abattre trois arbres dans le jardin de l'immeuble | 2024 |
| 7 m | Energy works | régulariser le placement d'une pompe à chaleur sur la toiture plate du deuxième étage en façade arrière de l'immeuble | 2024 |
| 7 m | Energy works | régulariser le placement d'une pompe à chaleur sur la toiture plate du deuxième étage en façade arrière de l'immeuble | 2025 |
| 37 m | Tree felling | abattre trois arbres dans le jardin de l'immeuble | 2026 |
| 39 m | Regularisation | régulariser les travaux effectués dans la maison unifamiliale | 2024 |
Other nearby cases : 18/PU/1829455, 18/PU/2026886, 18/PU/2040399, 18/PU/1864082, 18/PFD/2020505, 18/PU/1826321, 18/PU/1900221, 18/PU/2004469, 18/PU/1845559, 18/PU/2041292, 18/PU/2024294, 18/PU/1987089, 18/PU/2020504, 18/PU/1992740, 18/PU/1892334, 18/GOU_PU/1843433, 18/PU/1826290, 18/PU/1903578, 18/PFU/2002888, 18/PFU/1858482, 18/PU/2037033, 18/PU/1914368, 18/PFU/1900553, 18/AA/1975889, 18/AA/1892524