Skip to content
AltUrb
Granted

Tomberg

Woluwe-Saint-Lambert · 18/PFD/111008-01 · Permis d'urbanisme délivré par le FD

Tomberg, Woluwe-Saint-Lambert: —. Case octroyé, lodged on 24 April 1997. The decision was notified on 12 January 1998, 263 days after lodging.

Key figures
Permit typePermis d'urbanisme délivré par le FD
StatusOctroyé
Lodged on24 April 1997date the file was received
Consultation committee18 September 1997
Decision notified12 January 1998263 days
Floor areasnot reported by the source
Competent authorityBUP

Timeline

  1. Application lodged
  2. Consultation committee
  3. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.