Granted
Avenue de la Spirale
Woluwe-Saint-Lambert · 18/PFD/120980-01 · Permis d'urbanisme délivré par le FD
Avenue de la Spirale, Woluwe-Saint-Lambert: new construction. Case octroyé, lodged on 22 December 1998. The decision was notified on 2 September 1999, 254 days after lodging.
Placer 3 pavillons pour jeunes en contrebas de l'av. de la Spirale sur les terrains du stade communal| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 22 December 1998 | date the file was received |
| Consultation committee | 25 March 1999 | |
| Decision notified | 2 September 1999 | 254 days |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)
