Rue des Déportés 55, Woluwe-Saint-Lambert: façade and windows. Case octroyé, lodged on 17 January 2011. The decision was notified on 3 June 2011, 137 days after lodging.
isoler et mettre sous crépis d'un mur pignon| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 17 January 2011 | date the file was received |
| Decision notified | 3 June 2011 | 137 days |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 43 m | Extension or raising | démolir les annexes existantes, aménager une extension au rez-de-chaussée et isoler la façade arrière de l'immeuble | 2023 |
| 43 m | Extension or raising | régulariser les travaux effectués (le remplacement des menuiseries extérieures, la construction d'annexes en façade arri | 2025 |
| 56 m | Change of use | supprimer le commerce existant au rez-de-chaussée pour aménager un 2e logement en duplex en y intégrant une partie du so | 2026 |
| 69 m | — | 18/PU/2044718 | 2026 |
| 84 m | Demolition and reconstruction | régulariser les travaux effectués (le placement d'un bardage en façade avant, les modifications effectuées à la toiture, | 2026 |
Other nearby cases : 18/PFD/1810236, 18/PU/1846604, 18/PU/1822234, 18/PU/2037296, 18/AA/1841749, 18/PU/1997779, 18/PU/1801231, 18/PU/1926090, 18/PU/1810541, 18/PU/1974536, 18/PU/1948933, 18/PU/2026648, 18/AA/1829531, 18/PFD/2031324, 18/PU/1974306, 18/PU/1846471, 18/PU/1974563, 18/PU/1965643, 18/PU/1961998, 18/PU/1863600, 19/PU/1902106, 19/PU/2027311, 18/PU/1925656, 18/PU/1824694, 18/PU/1898091