Parvis Saint-Henri

Woluwe-Saint-Lambert · 18/PFD/494727 · Permis d'urbanisme délivré par le FD

Parvis Saint-Henri, Woluwe-Saint-Lambert: new construction. Case octroyé, lodged on 27 November 2013. The decision was notified on 28 February 2014, 93 days after lodging.

Placer 3 box vélo.
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme délivré par le FD
StatusOctroyé
Lodged on27 November 2013date the file was received
Decision notified28 February 201493 days
Floor areasnot reported by the source
Competent authorityBUP

Timeline

  1. Application lodged
  2. Declared complete
  3. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.