Granted
Chemin de la Crète
Woluwe-Saint-Lambert · 18/PFD/590983 · Permis d'urbanisme délivré par le FD
Chemin de la Crète, Woluwe-Saint-Lambert: other. Case octroyé, lodged on 25 January 2016. The decision was notified on 16 March 2016, 51 days after lodging.
Implanter un relais de télécommunication sur un pylône existant sur un bâtiment .| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 25 January 2016 | date the file was received |
| Decision notified | 16 March 2016 | 51 days |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Other | Les installations actuelles du poste Haute Tension (transformateurs, cabine 36kV, armoires basses tension) arrivent en f | 2025 |
| 0 m | Other | Remplacer les installations actuelles du poste Haute Tension (transformateurs, cabine 36 kV, armoires basses tensions) a | 2025 |
| 64 m | Tree felling | Abattre 3 arbres | 2021 |
| 139 m | Signs and advertising | "CLASSE SANS SUITE" régulariser le placement d'une enseigne éclairée posée au sol sur le terrai bâti | 2026 |
| 139 m | Public space | Installer des signalétiques directionnelles et de localisation tels que panneaux d'informations, totems, poteaux et marq | 2024 |
Other nearby cases : 18/PU/1948707, 18/PU/1928088, 18/PU/1871605
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)