Pending
Parvis Saint-Henri
Woluwe-Saint-Lambert · 18/PFU/286980 · Permis d'urbanisme unique délivré par le FD
Parvis Saint-Henri, Woluwe-Saint-Lambert: heavy renovation. Case demandé, lodged on 21 October 2010.
Démonter et remonter une culée de l'Eglise Saint-Henri| Permit type | Permis d'urbanisme unique délivré par le FD | |
|---|---|---|
| Status | Demandé | |
| Lodged on | 21 October 2010 | date the file was received |
| Consultation committee | 15 March 2011 | |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Consultation committee
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)