Avenue du Péage

Woluwe-Saint-Lambert · 18/PU/1718948 · Permis d'urbanisme privé

Avenue du Péage, Woluwe-Saint-Lambert: new construction. Case octroyé, lodged on 10 July 2019. The decision was notified on 8 May 2020, 303 days after lodging. The project creates 437 m² of housing.

construire deux maisons unifamiliales avec garages sur le terrain
The application's own description, in its source language (FR). Source: Nova.
437
Housing floor area created
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on10 July 2019date the file was received
Decision notified8 May 2020303 days
Works started28 March 2024
Competent authorityWoluwe-Saint-Lambert

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Granted
  5. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
25 mFaçade and windowsisoler et enduire la façade avant et le mur pignon et régulariser le remplacement des portes et des châssis de la maison2023
36 mNew constructionplacer une installation fixe temporaire à usage commercial destinée à accueillir un bureau de vente des logements du pro2024
55 mHeavy renovationrevoir le système de production de chaleur et d’eau chaude sanitaire, réaménager le sous-sol et les locaux techniques, m2024
61 mEnergy worksrégulariser les installations techniques existantes et placer de nouvelles installations de refroidissement en toiture d2026
61 mEnergy worksCLASSE SANS SUITE - régulariser les installations techniques existantes et placer de nouvelles installations de refroidi2025

Other nearby cases : 18/PU/1904574, 18/PU/1851392, 18/PU/1945181, 18/AA/1830292, 18/PFD/1906628, 18/PU/1897626, 18/PU/1836467, 18/PU/1931724, 18/PU/1969312, 18/PU/1961537