Skip to content
AltUrb
Granted

Rue Solleveld 52

Woluwe-Saint-Lambert · 18/PU/1792269 · Permis d'urbanisme privé

Rue Solleveld 52, Woluwe-Saint-Lambert: new construction. Case octroyé, lodged on 15 February 1905. The decision was notified on 19 July 1915, 3 806 days after lodging.

Bâtir une maison
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on15 February 1905date the file was received
Decision notified19 July 19153 806 days
Floor areasnot reported by the source
Competent authorityWoluwe-Saint-Lambert

Timeline

  1. Application lodged
  2. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mRoofrégulariser la modification de teinte du revêtement de toiture de la maison unifamiliale2022
0 mExtension or raisingrehausser la façade arrière et la toiture, étendre le rez-de-chaussée et rénover la maison unifamiliale2021
5 mHeavy renovationrégulariser les modifications effectuées sur la maison unifamiliale (par rapport à la situation de droit)2025
52 mHeavy renovationrégulariser les travaux effectués et rénover la maison unifamiliale2022
53 mExtension or raisingeffectuer des transformations intérieures, rehausser la façade arrière pour étendre le deuxième étage et modifier les an2023

Other nearby cases : 18/PU/1857430, 18/PU/2019483, 18/PU/1841512, 18/PU/1926526, 18/PU/1826098, 18/PU/1900500, 18/PU/2021265, 18/PU/1911499, 18/PU/1905994, 18/PU/1931026, 18/PU/1998237, 18/PU/1981352, 18/PU/1862752, 18/PU/1892854, 18/SFD/1810665, 18/PU/1906483, 18/PU/1829909, 18/PU/2016710, 18/PU/2037741, 18/SFD/1800099, 18/PU/1957286, 18/PU/1960783, 18/PU/2000744, 18/PFD/1839889, 18/PU/1902601

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)