Skip to content
AltUrb
Granted

Rue de la Cambre 18

Woluwe-Saint-Lambert · 18/PU/1848581 · Permis d'urbanisme privé

Rue de la Cambre 18, Woluwe-Saint-Lambert: façade and windows. Case octroyé, lodged on 8 July 2022. The decision was notified on 20 October 2022, 104 days after lodging.

remplacer les garde-corps et rénover les terrasses en façades avant et latérale de l'immeuble
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on8 July 2022date the file was received
Decision notified20 October 2022104 days
Works started24 January 2023
Floor areasnot reported by the source
Competent authorityWoluwe-Saint-Lambert

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Granted
  5. Works started
  6. event_works_ended

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mTree fellingabattre quatre arbres dans le jardin de l'immeuble2025
61 mExtension or raisingrénover complètement l'immeuble, construire une annexe à l'arrière et isoler la maison de type 3 façades2024
61 mTree fellingabattre un arbre dans le jardin de l'immeuble2025
61 mTree fellingabattre un arbre dans le jardin de l'immeuble2026
67 mRegularisationrégulariser une maison unifamiliale2023

Other nearby cases : 18/PU/1917448, 18/PU/2018251, 18/SFD/1961163, 18/PU/1927320, 18/PU/2044242, 18/PU/1917447, 19/PU/1998008, 18/PU/2024460, 19/PU/1989135, 19/PU/1918038, 19/PU/1867134, 19/PU/1944586, 18/PU/1835975, 18/PU/2032967, 18/PU/1957502, 18/GOU_PU/2003770, 18/PU/1895037, 19/PU/1934354, 18/SFD/2018374, 18/PU/1999124, 19/PU/2008896, 18/PU/1846218, 18/AA/2044009, 18/PU/1981484, 19/PU/1851259

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)