Avenue des Eperviers 117–121, Woluwe-Saint-Pierre: operation of installations. Case octroyé, lodged on 8 September 2021. The decision was notified on 28 October 2025, 1 511 days after lodging.
Exploitation d'un immeuble de logements| Permit type | Permis d'environnement | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 8 September 2021 | date the file was received |
| Public inquiry | 11 August 2025 – 11 September 2025 | |
| Consultation committee | 2 October 2025 | |
| Decision notified | 28 October 2025 | 1 511 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 2 m | Merger of dwellings | régulariser la fusion de deux appartements au 5ème étage | 2025 |
| 29 m | Regularisation | régulariser l’appartement du 3e étage côté droit en façade arrière de l'immeuble | 2024 |
| 30 m | Regularisation | régulariser un appartement 1 chambre au 6e étage arrière gauche de l’immeuble à appartements | 2024 |
| 47 m | Tree felling | abattre 4 arbres | 2025 |
| 62 m | Façade and windows | isoler les façades et remplacer les garde-corps d'un immeuble à appartements | 2025 |
Other nearby cases : 19/AA/1823806, 19/PU/2008962, 19/PU/1982234, 19/GOU_PU/1950001, 19/PU/1909257, 19/PU/1952068, 19/PU/2036520, 02/PU/1860632, 02/PU/1982859, 19/PU/1909147, 19/PU/1841612, 02/PU/1954240, 19/PU/1931433, 19/PU/2044871, 02/PU/1970317, 02/PU/2008823, 02/PU/2007149, 19/PU/1916695, 19/PU/1828146, 19/PU/1900283, 19/PU/1912405, 19/PU/1927211, 02/PU/2039718, 19/PU/1926450, 19/PU/2008837
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)