Rue au Bois 569
Woluwe-Saint-Pierre · 19/IPE/1858581 · Permis d'environnement
Rue au Bois 569, Woluwe-Saint-Pierre: operation of installations. Case demandé, lodged on 18 October 2022.
Exploitation d'une marbrerie| Permit type | Permis d'environnement | |
|---|---|---|
| Status | Demandé | |
| Lodged on | 18 October 2022 | date the file was received |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 38 m | Tree felling | abattre un arbre en zone de cours et jardins | 2021 |
| 53 m | Extension or raising | régulariser, étendre et transformer une habitation unifamiliale | 2025 |
| 53 m | Extension or raising | Etendre et Transfer une habitation unifamiliale | 2025 |
| 65 m | Regularisation | régulariser une habitation unifamiliale mitoyenne | 2026 |
| 66 m | Heavy renovation | régulariser, isoler et transformer une habitation unifamiliale 3 façades | 2026 |
Other nearby cases : 19/PU/1862622, 19/PU/1861011, 19/PU/1980241, 19/PFD/1980032, 19/SFD/1823543, 19/PU/1904785, 19/PU/1911166, 19/PU/1968761, 19/PU/1944884, 19/PU/1853772, 19/PU/1827538, 19/PU/1855299, 19/PU/1983477, 19/PU/1850128, 19/PU/1989416, 19/PU/2028098, 19/PU/2033426, 19/PU/1849818, 19/AA/1929460, 19/PU/1910874, 19/PFD/1870405, 19/PU/1910454, 19/PU/1946925, 19/PU/2039936, 19/PU/2021043
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)