Skip to content
Altaica Urban
Granted

Avenue des Dames Blanches 88–94

Woluwe-Saint-Pierre · 19/IPEEXT/1842798 · Extension / Transformation de PE

Avenue des Dames Blanches 88–94, Woluwe-Saint-Pierre: operation of installations. Case octroyé, lodged on 23 May 2022. The decision was notified on 1 July 2022, 39 days after lodging.

modification
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typeExtension / Transformation de PE
StatusOctroyé
Lodged on23 May 2022date the file was received
Decision notified1 July 202239 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
37 mTree fellingabattre 3 arbres en zone de cours et jardins2022
37 mExtension or raisingextension et transformation de l'habitation unifamiliale mitoyenne2022
83 mDemolitiondémolir la véranda en façade arrière et régulariser l'habitation unifamiliale mitoyenne2025
88 mExtension or raisingRégulariser les travaux d'extension et de transformation2022
91 mTree fellingabattre 80 arbres2023

Other nearby cases : 19/AA/1849807, 19/SFD/1826833, 19/PU/1831841, 19/PU/1929730, 19/PU/2014930, 19/AA/2003591, 19/PU/1902110, 19/PU/1849794, 19/PU/2026697, 19/PU/1900909, 19/PU/1833862, 19/PU/1866178, 19/PU/2037710, 19/PU/1993355, 19/PFU/1903877, 19/PU/1912895, 19/PU/1830821, 19/PU/1870312, 19/SFD/1838360, 19/PU/1967497, 19/PFD/1995894, 19/PFD/2025449, 19/PFD/2011440, 19/PU/1938876, 19/PFD/1834370

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)