Avenue du Val d'Or 90
Woluwe-Saint-Pierre · 19/IPEEXT/455309 · Extension / Transformation de PE
Avenue du Val d'Or 90, Woluwe-Saint-Pierre: operation of installations. Case annulé, lodged on 6 July 2009. The decision was notified on 22 July 2009, 16 days after lodging.
stopzetting ondergrondse tanks 2*10000l, ondergrondse tank 5000l en bovengrondse tank 9000 l| Permit type | Extension / Transformation de PE | |
|---|---|---|
| Status | Annulé | |
| Lodged on | 6 July 2009 | date the file was received |
| Decision notified | 22 July 2009 | 16 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Decision notified · Withdrawn
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 46 m | Energy works | Placer une pompe à chaleur en zone de recul de la maison unifamiliale | 2023 |
| 69 m | Regularisation | régulariser un immeuble à appartements | 2024 |
| 81 m | Heavy renovation | régulariser les transformations et les aménagements intérieurs des 3 appartements | 2024 |
| 96 m | Regularisation | régularisation d'une maison unifamiliale | 2021 |
| 96 m | Extension or raising | étendre et régulariser une habitation unifamiliale mitoyenne | 2025 |
Other nearby cases : 19/SFD/1853280, 19/PU/1984899, 19/PU/2021058, 19/PU/1979593, 19/PU/2016839, 19/PU/2017766, 19/PU/1972858, 19/PU/1902062, 19/PU/1869503, 19/SFD/1840192, 18/PU/2038967, 18/PU/1940996, 19/PU/1947480, 19/PU/1967248, 19/PU/2024800, 19/PU/1938894, 19/PU/1831004, 19/PU/2004182, 18/PU/1850046, 19/PU/1943595, 18/PU/1960727, 19/PU/1902219, 18/PU/1973180, 19/PU/2020241, 18/PU/1902183