Altaica Urban
Granted

Avenue Orban 115

Woluwe-Saint-Pierre · 19/IPETMP/2038360 · Permis d'environnement temporaire

Avenue Orban 115, Woluwe-Saint-Pierre: operation of installations. Case octroyé, lodged on 8 July 2026. The decision was notified on 26 August 2026, 49 days after lodging.

Verwijderen van leidingisolatie in kelder en vloerbekleding op +1
The application's own description, in its source language (NL). Source: Nova.
Key figures
Permit typePermis d'environnement temporaire
StatusOctroyé
Lodged on8 July 2026date the file was received
Decision notified26 August 202649 days
Works started14 September 2026
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Granted
  5. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
12 mNew constructionconstruire un garage et une piscine extérieure, transformer et régulariser l'habitation unifamiliale 4 façades2025
12 mExtension or raisingétendre en sous-sol une maison unifamiliale2025
42 mExtension or raisingrehausser, isoler et transformer une habitation unifamiliale isolée2026
79 mExtension or raisingextension en façade arrière d’une habitation unifamiliale existante2026
79 mHeavy renovationrégulariser et installer un ascenseur et un feu ouvert dans une maison unifamiliale2023

Other nearby cases : 19/PU/2031442, 19/PU/1939128, 19/SFD/1845392, 19/PU/1962185, 19/PU/2013953, 19/AA/1925502

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)