Granted

Rue du Bemel 122

Woluwe-Saint-Pierre · 19/PFD/135366 · Permis d'urbanisme délivré par le FD

Rue du Bemel 122, Woluwe-Saint-Pierre: new construction. Case octroyé, lodged on 2 March 2001. The decision was notified on 28 August 2002, 544 days after lodging.

Construire un réfectoire et d'un préau
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme délivré par le FD
StatusOctroyé
Lodged on2 March 2001date the file was received
Consultation committee25 January 2002
Decision notified28 August 2002544 days
Floor areasnot reported by the source
Competent authorityBUP

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Consultation committee
  5. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
76 mDemolition and reconstructiondémolir et reconstruire la véranda au rez-de-chaussée en façade arrière2024
86 mFaçade and windowsRemplacer la porte de garage d'une maison unifamiliale2023
88 mRegularisationrégularisation d'une maison unifamiliale2022
91 mTree fellingabattre un arbre2026
98 mRegularisationrégulariser un appartement2024

Other nearby cases : 19/PU/1965168, 19/AA/1825347, 19/PU/1850079, 19/PU/2023113, 19/PU/1972133, 19/PU/1996792, 19/PU/1947231, 19/PU/1841727, 19/AA/1852543, 19/PU/1839419, 19/AA/1891911, 19/PU/1836768, 19/PFD/1979967, 19/PU/1980309, 19/PU/1899468, 19/SFD/1832199, 19/PU/1952379, 19/AA/1988659, 19/PU/1909387, 19/PU/1810232, 19/AA/1937301, 19/PU/1892567, 19/PU/1939512, 19/PU/1926997, 19/PU/1991636

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)