Granted
Rue de la Limite
Woluwe-Saint-Pierre · 19/PFD/158948 · Permis d'urbanisme délivré par le FD
Rue de la Limite, Woluwe-Saint-Pierre: new construction. Case octroyé, lodged on 17 September 2004. The decision was notified on 24 February 2005, 160 days after lodging.
construire un centre communautaire 'Centre Amitié', à la Cité de l'Amitié,| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 17 September 2004 | date the file was received |
| Decision notified | 24 February 2005 | 160 days |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)