Skip to content
AltUrb
Granted

Rue au Bois 365

Woluwe-Saint-Pierre · 19/PFU/1869119 · Permis d'urbanisme unique délivré par le FD

Rue au Bois 365, Woluwe-Saint-Pierre: energy works. Case octroyé, lodged on 20 January 2023. The decision was notified on 5 July 2023, 166 days after lodging.

Placer des capteurs photovoltaïques sur les toitures de deux bâtiments
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme unique délivré par le FD
StatusOctroyé
Lodged on20 January 2023date the file was received
Decision notified5 July 2023166 days
Works started16 August 2023
Floor areasnot reported by the source
Competent authorityBUP

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Granted
  5. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mTree fellingabattre 13 arbres2022
30 mNew constructionRénover afin d'améliorer la performance énergétique des bâtiments ABC D et E; ajouter un étage au bâtiment D; construire2026
113 mTree fellingabattre un arbre en zone de cours et jardins2021
130 mRegularisationrégulariser un appartement situé au 11ème étage (170DD) d'un immeuble à appartements2025
130 mTree fellingabattre 10 arbres2024

Other nearby cases : 19/AA/1913147, 19/PU/2042311, 19/PU/2024670, 19/AA/1976036, 19/PU/1964844, 19/PU/1934304, 19/PU/1833222, 19/PFD/1829680, 19/PFD/1893013, 19/PU/1863127, 19/PFU/1870494, 19/AA/1856707, 19/PU/1850908, 19/PU/2029553, 19/AA/1825178, 19/SFD/1849620, 19/PU/1830898, 19/PU/1846231, 19/PU/2022206, 19/PU/1864360, 19/PU/1834828, 19/PU/2036687, 19/PU/2004921, 19/PU/1867765, 19/SFD/1831334

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)