Granted
Chemin de Ronde
Woluwe-Saint-Pierre · 19/PFU/2008778 · Permis d'urbanisme unique délivré par le FD
Chemin de Ronde, Woluwe-Saint-Pierre: tree felling. Case octroyé, lodged on 7 November 2025. The decision was notified on 1 December 2025, 24 days after lodging.
abattre 47 arbres pour raisons phytosanitaires , 2 sécurisations par réduction et 3 régularisations ;
11 plantations d'arbres| Permit type | Permis d'urbanisme unique délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 7 November 2025 | date the file was received |
| Decision notified | 1 December 2025 | 24 days |
| Works started | 14 September 2026 | |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 48 m | Tree felling | Abattre 9 arbres et régulariser un arbre abattu au Parc Parmentier. | 2022 |
| 67 m | Tree felling | Abattre 31 arbres | 2025 |
| 133 m | Tree felling | abattre 2 arbres en zone de cours et jardins | 2023 |
| 138 m | Other | Voorliggende aanvraag heeft betrekking op het verkrijgen van een nachtvergunning ( de nacht van 18/04 op 19/04) om borin | 2024 |
| 138 m | Public space | boren 's nachts in de buurt van tramsporen | 2024 |
Other nearby cases : 19/PFU/1925172, 19/PFU/1955425, 19/PFU/1931581, 19/PFU/1910427, 19/PFU/1982282, 19/PU/1977793, 19/PU/1931407, 19/PFU/1927306, 19/PFU/1928415