Bovenberg 122
Woluwe-Saint-Pierre · 19/PFU/555263 · Permis d'urbanisme unique délivré par le FD
Bovenberg 122, Woluwe-Saint-Pierre: extension or raising. Case octroyé, lodged on 18 December 2014. The decision was notified on 2 May 2017, 866 days after lodging. The project creates 23 m² of housing.
Transformer et étendre un logement. Transformer et étendre un poulailler existant en atelier d'artiste, accessoire au logement.| Permit type | Permis d'urbanisme unique délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 18 December 2014 | date the file was received |
| Public inquiry | 29 August 2016 – 13 September 2016 | |
| Consultation committee | 22 September 2016 | |
| Decision notified | 2 May 2017 | 866 days |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 24 m | Change of use | régulariser les travaux de transformation d'un "poolhouse" et l'aménagement d'un atelier d'artiste en studio | 2023 |
| 64 m | Regularisation | régulariser deux bâtiments situés sur la propriété | 2023 |
| 85 m | Other | Sécuriser le poste de fourniture électrique selon les dernières normes en vigueur de SIBELGA et ELIA au moyen de l'insta | 2026 |
| 127 m | Heavy renovation | Rénover la couverture en ardoises naturelle du château, peindre les colombages et les châssis, réaménager le 2e étage et | 2022 |
| 133 m | Tree felling | abattre 5 arbres | 2022 |
Other nearby cases : 19/PFU/1929100, 19/PU/2013729, 19/PU/1938891, 19/PFU/1962044, 19/PU/1927474, 19/PU/1985060, 19/PFU/1864403, 19/PFU/1849851, 19/PU/1929123, 19/PU/1828110, 19/SFD/1837312, 19/PFU/1956584, 19/PFU/2015271, 19/PFD/1841208, 19/PFU/1866382, 19/AA/1855999, 19/PFU/1983101, 19/PU/2043792, 02/GOU_PU/1826547, 19/PFU/1928415, 19/PU/1994141, 19/PU/1811056, 19/SFD/1839581, 19/AA/1852951, 19/PFU/1908757