Skip to content
Altaica Urban
Granted

Avenue des Fleurs 28

Woluwe-Saint-Pierre · 19/PU/1702367 · Permis d'urbanisme privé

Avenue des Fleurs 28, Woluwe-Saint-Pierre: extension or raising. Case octroyé, lodged on 12 February 2019. The decision was notified on 20 June 2019, 128 days after lodging. The project creates 208 m² of housing.

Étendre et transformer deux habitations unifamiliales
The application's own description, in its source language (FR). Source: Nova.
208
Housing floor area created
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on12 February 2019date the file was received
Public inquiry6 March 2019 – 21 March 2019
Consultation committee28 March 2019
Decision notified20 June 2019128 days
Competent authorityWoluwe-Saint-Pierre

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Public inquiry opened
  5. Public inquiry closed
  6. Consultation committee
  7. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
10 mOtherconstruire une piscine à ciel ouvert dans le jardin2023
128 mExtension or raisingrégulariser, étendre et transformer une maison unifamiliale isolée avec construction d'une piscine et abattage de 4 arbr2025
137 mTree fellingabattre un arbre en zone de cours et jardins2023
143 mTree fellingabattre un arbre en zone de cours et jardins2022
145 mHeavy renovationrégulariser et recréer un garage dans l'habitation unifamiliale 4 façades2022

Other nearby cases : 19/PU/2009773, 19/AA/1823953, 19/PFD/1898071, 19/AA/1823910, 19/PU/1962185, 19/AA/1983887, 19/SFD/1845392, 19/PU/1831677, 19/AA/1823645, 19/AA/1929675, 19/PU/1828136, 19/SFD/1838026, 19/SFD/1842292, 19/PU/2031442

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)