Rue du Bemel 79, Woluwe-Saint-Pierre: extension or raising. Case octroyé, lodged on 13 March 2019. The decision was notified on 11 July 2019, 120 days after lodging. The project creates 9 m² of housing.
Etendre et transformer une habitation unifamiliale mitoyenne| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 13 March 2019 | date the file was received |
| Public inquiry | 29 April 2019 – 15 May 2019 | |
| Consultation committee | 23 May 2019 | |
| Decision notified | 11 July 2019 | 120 days |
| Competent authority | Woluwe-Saint-Pierre |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 12 m | Façade and windows | Remplacer la porte de garage d'une maison unifamiliale | 2023 |
| 24 m | Demolition and reconstruction | démolir et reconstruire la véranda au rez-de-chaussée en façade arrière | 2024 |
| 53 m | Roof | isoler la toiture et les lucarnes par l'extérieur et remplacer les gardes-corps des combles de l'immeuble à appartements | 2022 |
| 67 m | Heavy renovation | transformer la maison unifamiliale | 2023 |
| 69 m | Heavy renovation | isoler et transformer une maison unifamiliale | 2024 |
Other nearby cases : 19/PU/1996792, 19/PU/1972133, 19/PU/2036973, 19/AA/1988659, 19/SFD/1832199, 19/AA/1852543, 19/PU/1952379, 19/PU/1842404, 19/PU/1965168, 19/PU/1992721, 19/PU/1843749, 19/AA/1866351, 19/PU/2017663, 19/PU/2020177, 19/AA/1825347, 19/PU/1939512, 19/PU/1892567, 19/PU/1866079, 19/PU/2014255, 19/PU/1850079, 19/PU/2023113, 19/PU/1929584, 19/PU/1912891, 19/PU/1899161, 19/PU/1901109
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)