Rue de l'Eglise 74

Woluwe-Saint-Pierre · 19/PU/1741910 · Permis d'urbanisme privé

Rue de l'Eglise 74, Woluwe-Saint-Pierre: heavy renovation. Case octroyé, lodged on 18 February 2020. The decision was notified on 17 July 2020, 150 days after lodging.

Ajouter une chambre à l'appartement du 1er étage
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on18 February 2020date the file was received
Decision notified17 July 2020150 days
Floor areasnot reported by the source
Competent authorityWoluwe-Saint-Pierre

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mExtension or raisingEtendre la pizzeria du 74A au 76A2022
15 mTree fellingRégulariser l'abattage de 2 arbres en zone de cours et jardins2023
28 mExtension or raisingExtension d'une maison unifamiliale2022
47 mOtherMettre en conformité l'installation station télécommunication sur une structure existante sur la toiture de l'église Not2025
52 mChange of useChangement d'affectation du rez-de-chaussée commercial en équipement d’intérêt collectif2022

Other nearby cases : 19/PU/1869358, 19/PU/1851167, 19/PU/2032150, 19/PU/1850069, 19/PU/1911035, 19/PU/1969754, 19/PU/1827710, 19/PU/1955151, 19/PU/1846377, 19/GOU_PU/1953179, 19/PU/1927459, 19/PU/1924068, 19/PU/2004932, 19/PU/1839349, 19/PU/1990045, 19/AA/1915144, 19/PU/1953764, 19/PU/1835708, 19/PU/1925076, 19/PU/1892221, 19/PU/1909781, 19/PU/1922559, 19/GOU_PU/1998003, 19/PU/1947790, 19/PU/1958034

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)