Granted

Avenue Orban 74

Woluwe-Saint-Pierre · 19/PU/1748757 · Permis d'urbanisme privé

Avenue Orban 74, Woluwe-Saint-Pierre: other. Case octroyé, lodged on 4 May 2020. The decision was notified on 22 January 2021, 263 days after lodging. The project creates 3 m² of housing.

aménagement d'un portail d'entrée et régularisation des modifications dans une maison unifamiliale isolée
The application's own description, in its source language (FR). Source: Nova.
3
Housing floor area created
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on4 May 2020date the file was received
Consultation committee24 September 2020
Decision notified22 January 2021263 days
Works started28 October 2021
Competent authorityWoluwe-Saint-Pierre

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Consultation committee
  5. Decision notified · Granted
  6. Works started
  7. event_works_ended

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
26 mTree fellingabattre un arbre en zone de recul2025
75 mTree fellingAbattre un arbre en zone de recul2022
85 mExtension or raisingétendre et transformer l'habitation unifamiliale 4 façades2023
89 mTree fellingabattre 4 arbres en zone de recul2026
92 mTree fellingAbattre un arbre en zone de cours et jardins2022

Other nearby cases : 19/AA/1838895, 19/PFD/2006563, 19/PU/2005015, 19/PU/1933671, 19/PU/1853798, 19/PU/1897200, 19/PU/2015000, 19/PU/1964376, 19/AA/1960073, 19/PU/1996761, 19/PFD/1862418, 19/PU/1930752, 19/AA/1926727, 19/AA/1912263, 19/AA/1953358, 19/PU/1984069, 19/PU/1915173, 19/PU/1967067, 19/PU/2005136, 19/PU/1961231, 19/PU/1853780, 19/PU/2037429, 19/PU/2011312, 19/PU/2001404, 19/PU/1952673

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)