Granted

Rue du Bemel 166

Woluwe-Saint-Pierre · 19/PU/1775434 · Permis d'urbanisme privé

Rue du Bemel 166, Woluwe-Saint-Pierre: roof. Case octroyé, lodged on 4 January 2021. The decision was notified on 27 August 2021, 235 days after lodging.

Isolation de la toiture via l'extérieur d'une habitation 3 façades
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on4 January 2021date the file was received
Decision notified27 August 2021235 days
Works started2 May 2022
Floor areasnot reported by the source
Competent authorityWoluwe-Saint-Pierre

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Granted
  5. Works started
  6. event_works_ended

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
10 mExtension or raisingétendre et transformer une maison unifamiliale2024
57 mRoofmodifier la toiture d'une maison unifamiliale2025
57 mTree fellingAbattre 1 arbre en zone latérale2023
75 mHeavy renovationisoler et transformer une maison unifamiliale2024
80 mExtension or raisingétendre, transformer et régulariser une habitation unifamiliale mitoyenne2023

Other nearby cases : 19/PU/1916128, 19/PU/1937742, 19/PU/1908857, 19/AA/1835208, 19/PU/1825762, 19/AA/1867834, 19/PU/1826621, 19/PU/2033873, 19/PU/2007301, 19/PU/1849871, 19/PU/2024218, 19/PU/1909387, 05/PU/1970394, 19/PU/1975660, 05/PU/1843191, 19/PU/1939356, 19/PU/1952379, 19/PU/1811531, 19/SFD/1847596, 19/PU/1850109, 19/PU/1965168, 19/PU/2039478, 05/PU/2015871, 19/PU/2031149, 19/PU/1851257