Granted

Rue du Bemel 115

Woluwe-Saint-Pierre · 19/PU/1787963 · Permis d'urbanisme privé

Rue du Bemel 115, Woluwe-Saint-Pierre: roof. Case octroyé, lodged on 29 April 2021. The decision was notified on 6 October 2021, 160 days after lodging. The project creates 8 m² of housing.

Réaménagement intérieur , isolation de la toiture par l'extérieur et aménagement d'une lucarne en façade arrière de l'habitation unifamiliale mitoyenne ;
The application's own description, in its source language (FR). Source: Nova.
8
Housing floor area created
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on29 April 2021date the file was received
Decision notified6 October 2021160 days
Works started10 January 2022
Competent authorityWoluwe-Saint-Pierre

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Granted
  5. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
22 mTree fellingabattre un arbre2026
48 mTree fellingabattre un arbre en zone de cours et jardins2022
50 mRoofrénover et isoler la toiture et les lucarnes d'un immeuble de logements2024
59 mTree fellingabattre de 3 arbres en zone de cours et jardins2024
72 mTree fellingabattre un arbre en zone de cours et jardins2025

Other nearby cases : 19/PU/1996792, 19/PU/1941499, 19/PU/2023113, 19/PU/1850079, 19/PU/2033873, 19/PU/1842404, 19/PU/2020177, 19/PU/1841727, 19/PU/1908943, 19/AA/1867834, 19/PU/1826621, 19/PU/1937742, 19/PU/1909387, 19/PU/1908857, 19/PU/1912891, 19/PU/1899468, 19/AA/1835208, 19/PU/1947231, 19/AA/1834041, 19/AA/1988659, 19/PU/1850109, 19/PU/1992721, 19/PU/1866079, 19/AA/1866351, 19/PU/1843749

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)