Rue du Collège Saint-Michel 30, Woluwe-Saint-Pierre: regularisation. Case octroyé, lodged on 31 January 2022. The decision was notified on 25 October 2022, 267 days after lodging.
régularisation d'un appartement situé en 3ème étage d'un immeuble à appartements| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 31 January 2022 | date the file was received |
| Decision notified | 25 October 2022 | 267 days |
| Competent authority | Woluwe-Saint-Pierre |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 58 m | Regularisation | Mise en conformité d’une habitation unifamiliale | 2024 |
| 71 m | Roof | rehausser les garde-corps des terrasses périphériques du dernier étage en façades avant | 2025 |
| 81 m | Extension or raising | transformer, rénover et ajouter un étage à l'immeuble mitoyen | 2025 |
| 90 m | Extension or raising | régularisation des façades et de l’extension du sous sol | 2021 |
| 91 m | Extension or raising | modifier la répartition des logements, le bow-window en façade avant et la hauteur de l'immeuble mitoyen | 2026 |
Other nearby cases : 19/PU/1968529, 19/PU/1937898, 19/PU/1850017, 19/PU/1867780, 19/PFD/1904975, 19/PU/2031630, 19/PU/2017098, 19/PU/1914965, 19/PU/1949649, 19/PU/2025951, 19/PFU/2042563, 19/PU/2035476, 19/PU/1950384, 19/PU/1989473, 19/PU/1974609, 19/PU/1950407, 19/PFU/1939210, 19/PU/1938861, 19/PU/1934128, 19/PFU/1948881, 19/PU/1907280, 19/PFU/1948879, 19/PU/2012225, 19/PFD/2028816, 19/PU/2024393