Avenue Van Crombrugghe 113, Woluwe-Saint-Pierre: extension or raising. Case octroyé, lodged on 2 March 2022. The decision was notified on 27 June 2023, 482 days after lodging. The project creates 24 m² of housing.
Transformer et étendre la maison unifamiliale| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 2 March 2022 | date the file was received |
| Decision notified | 27 June 2023 | 482 days |
| Competent authority | Woluwe-Saint-Pierre |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 6 m | Roof | aménager les combles et régulariser l'habitation unifamiliale mitoyenne | 2022 |
| 26 m | Change of use | modifier un logement en commerce et placer deux enseignes en façade avant d'une maison bi familiale | 2023 |
| 41 m | Extension or raising | étendre une maison unifamiliale 2 façades | 2026 |
| 45 m | Change of use | changement d'affectation d'un commerce avec modification des façades (points de retrait) | 2022 |
| 60 m | Extension or raising | Régulariser la pose d'un box à vélos 5 places | 2022 |
Other nearby cases : 19/PU/2027148, 19/PU/1897369, 19/PU/1897071, 19/PFD/2011440, 19/PFD/2025449, 19/PU/1826637, 19/PFD/1995894, 19/PU/1926708, 19/PU/1868296, 19/PU/1868023, 19/PU/1914114, 19/PU/1957254, 19/AA/1843928, 19/PU/1995025, 19/PU/1846301, 19/PU/1914235, 19/PU/1849794, 19/PU/2026697, 19/PU/1993355, 19/PU/1967497, 19/PU/1830821, 19/SFD/1838360, 19/PU/1961810, 19/PU/1917253, 19/PU/1811128