Avenue Baron Albert d'Huart 104
Woluwe-Saint-Pierre · 19/PU/1860116 · Permis d'urbanisme privé
Avenue Baron Albert d'Huart 104, Woluwe-Saint-Pierre: heavy renovation. Case octroyé, lodged on 17 October 2022. The decision was notified on 2 June 2023, 228 days after lodging. The project creates 9 m² of housing.
modifier un immeuble bifamilial| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 17 October 2022 | date the file was received |
| Public inquiry | 6 March 2023 – 21 March 2023 | |
| Consultation committee | 30 March 2023 | |
| Decision notified | 2 June 2023 | 228 days |
| Competent authority | Woluwe-Saint-Pierre |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
- event_works_ended
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Extension or raising | régulariser une terrasse à l'arrière d'une maison bi-familiale | 2024 |
| 0 m | Extension or raising | régulariser une terrasse à l'arrière d'une maison bi-familiale | 2024 |
| 14 m | Heavy renovation | transformer et régulariser un immeuble de 3 logements | 2023 |
| 49 m | Tree felling | abattre un arbre en zone de cours et jardins | 2022 |
| 49 m | Heavy renovation | transformer, régulariser et isoler une maison unifamiliale | 2023 |
Other nearby cases : 19/SFD/1856172, 19/PU/1957119, 19/PU/2007885, 19/PU/1932700, 19/PU/1870871, 19/PU/1986977, 19/PU/2013298, 19/PU/1895718, 19/PU/1851267, 19/PU/1976460, 19/AA/1938078, 19/PU/1831644, 19/SFD/1845163, 19/AA/2039875, 19/PU/1897098, 19/AA/1915903, 19/PU/1896704
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)