Avenue Orban 193
Woluwe-Saint-Pierre · 19/PU/1904853 · Permis d'urbanisme privé
Avenue Orban 193, Woluwe-Saint-Pierre: energy works. Case refusé, lodged on 31 May 2023. The decision was notified on 26 July 2024, 422 days after lodging.
placer une cabine à haute-tension, 4 cabines électriques et créer 4 emplacements de parking pour la recharge de voitures électriques| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Refusé | |
| Lodged on | 31 May 2023 | date the file was received |
| Public inquiry | 6 November 2023 – 21 November 2023 | |
| Consultation committee | 30 November 2023 | |
| Decision notified | 26 July 2024 | 422 days |
| Floor areas | — | not reported by the source |
| Competent authority | Woluwe-Saint-Pierre |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Refused
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 18 m | Heavy renovation | Modifier des baies et l'aménagement intérieur (Modification du PU DB005/2020) | 2022 |
| 46 m | Tree felling | Abattre un arbre | 2022 |
| 46 m | Tree felling | abattre un arbre en zone de recul | 2023 |
| 46 m | Tree felling | Abattre un arbre | 2022 |
| 53 m | Extension or raising | étendre, transformer et régulariser le commerce HORECA et le studio dans les combles | 2025 |
Other nearby cases : 19/PU/1896704, 19/PU/1822812, 19/PU/1811480, 19/PU/1897098, 19/AA/2039875, 19/SFD/1845163, 19/PU/1962862, 19/AA/1913261, 19/PU/1832486, 19/PU/1915182, 19/PU/2027062, 19/PU/1831644, 19/PU/1986666, 19/PU/1979782, 19/PU/1851267, 19/PU/2013298, 19/PU/1903744, 19/PU/2014434, 19/PU/1931389, 19/PU/1895718, 19/PFD/1962324, 19/PU/1962620, 19/PU/1947646, 19/PU/1851419, 19/PU/1950841
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)