Avenue de Tervueren 250, Woluwe-Saint-Pierre: office conversion. Case octroyé, lodged on 20 October 2023. The decision was notified on 28 February 2024, 131 days after lodging. The project creates 147 m² of housing.
veranderen van een kantoor tot woonruimte| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 20 October 2023 | date the file was received |
| Decision notified | 28 February 2024 | 131 days |
| Works started | 22 April 2024 | |
| Competent authority | Woluwe-Saint-Pierre |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 45 m | Split into dwellings | Transformer deux chambres de bonne et un local "voitures d'enfants" en studio | 2025 |
| 45 m | Regularisation | régulariser l'appartement gauche au 1er étage de l'immeuble | 2022 |
| 45 m | Split into dwellings | Régularisation de la division entre 2 appartements | 2021 |
| 60 m | New construction | Transformer un immeuble de bureaux en un immeuble mixte comportant 50 logements, 664m² d’équipement, 391 m² de bureaux ( | 2025 |
| 78 m | Public space | créer deux rampes d'accès devant les entrées n°310 et n°312 | 2023 |
Other nearby cases : 19/PU/1831754, 19/PU/1891712, 19/PU/2018112, 19/PU/1999418, 19/PU/1950111, 19/PU/1831156, 19/PU/1909615, 19/GOU_PU/2009560, 19/PU/1903417, 19/PU/1908849, 19/PFU/1831791, 19/PU/2041426, 19/PU/2001800, 19/AA/1848099, 19/PU/2041006, 19/PU/1826736, 19/PU/2015315, 19/PU/1841542, 19/AA/1938279, 19/PU/1933369, 19/PU/1954931, 19/PU/1943084, 19/PU/2000420, 19/PU/2014773, 19/PFU/1891855