Bemelstraat 56
Woluwe-Saint-Pierre · 19/PU/1939512 · Permis d'urbanisme privé
Bemelstraat 56, Woluwe-Saint-Pierre: new construction. Case octroyé, lodged on 8 April 2024. The decision was notified on 6 March 2025, 332 days after lodging. The project creates 335 m² of housing.
bouwen van een ééngezinswoning| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 8 April 2024 | date the file was received |
| Public inquiry | 26 August 2024 – 10 September 2024 | |
| Consultation committee | 19 September 2024 | |
| Decision notified | 6 March 2025 | 332 days |
| Works started | 24 September 2025 | |
| Competent authority | Woluwe-Saint-Pierre |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | New construction | construire un immeuble à appartements | 2023 |
| 23 m | Façade and windows | remplacement des châssis dans un appartement | 2023 |
| 23 m | Regularisation | regulariser un studio | 2023 |
| 44 m | Façade and windows | remplacer les châssis extérieurs d’une maison unifamiliale avec modification du matériau et de la teinte | 2026 |
| 57 m | Regularisation | régulariser l’appartement du 3e étage gauche en façade avant de l'immeuble à appartements | 2024 |
Other nearby cases : 19/PU/1915105, 19/PU/1904613, 19/PU/1913404, 19/PU/1810232, 19/PU/1969481, 19/PU/1973991, 19/PU/1947231, 19/SFD/1832199, 19/PU/1957617, 19/PU/1825102, 19/SFD/1832886, 19/PU/1851416, 19/AA/1825347, 19/PU/1942623, 19/PU/1979374, 19/AA/1988659, 19/PU/1908943, 19/PU/1899468, 19/PU/1961186, 19/PU/1971898, 19/PU/1991636, 19/PU/1993294, 19/PU/1947685, 19/AA/1891911, 19/PU/1941499