Granted

Rue des Hiboux 69

Woluwe-Saint-Pierre · 19/PU/1949796 · Permis d'urbanisme privé

Rue des Hiboux 69, Woluwe-Saint-Pierre: extension or raising. Case octroyé, lodged on 2 July 2024. The decision was notified on 15 October 2024, 105 days after lodging. The project creates 199 m² of housing.

construire un sous-sol à l'habitation unifamiliale mitoyenne et abattre un arbre
The application's own description, in its source language (FR). Source: Nova.
199
Housing floor area created
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on2 July 2024date the file was received
Decision notified15 October 2024105 days
Works started3 November 2025
Competent authorityWoluwe-Saint-Pierre

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Granted
  5. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mNew constructionconstruire une habitation unifamiliale mitoyenne2023
10 m19/PU/18308572021
10 mNew constructionconstruire une habitation unifamiliale 2 façades2022
13 mTree fellingabattre 1 arbre en zone de cours et jardins2023
15 mNew constructionconstruire une habitation unifamiliale 3 façades2023

Other nearby cases : 19/PU/2009144, 19/PU/1857890, 19/PU/2009294, 19/SFD/1835150, 19/PU/1825801, 19/PFD/1909271, 19/PFD/1861660, 19/PFD/1810399, 19/PU/1835127, 19/PU/1907861, 19/PU/1955761, 19/PU/1863178, 19/PU/1830659, 19/PU/1996454, 19/PU/2000775, 19/PU/1908126, 19/PU/2002385, 19/GOU_PU/1989547, 19/PU/1960696, 19/PU/1866707, 19/PU/1952493, 19/PU/2029304, 19/PU/1866815, 19/PU/1984664, 19/PU/1958065