Chaussée de Stockel 377, Woluwe-Saint-Pierre: demolition and reconstruction. Case octroyé, lodged on 23 July 2022. The decision was notified on 31 July 2023, 373 days after lodging. The project creates 114 m² of housing. It comprises 3 dwellings.

Démolir un bâtiment et construire un immeuble mixte composé d'un commerce et de 3 unités de logements
The application's own description, in its source language (FR). Source: Nova.
114
Housing floor area created
3
Dwellings created
Key figures
Permit typePermis d'urbanisme – saisine du fonctionnaire délégué
StatusOctroyé
Lodged on23 July 2022date the file was received
Decision notified31 July 2023373 days
Competent authorityBUP

Timeline

  1. Application lodged
  2. Decision notified · Granted
  3. event_works_ended

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mNew constructionConstruction d'un immeuble mixte composé d'un commerce et de 3 unités de logements2021
23 mRoofcréer deux lucarnes en toiture, isoler la façade arrière et les extensions et transformer une habitation unifamiliale mi2026
26 mRoofrégulariser, créer une lucarne en façade arrière et isoler le pignon mitoyen et la façade arrière d'une habitation unifa2026
71 mHeavy renovationrégulariser et transformer un immeuble de rapport2025
79 mTree fellingabattre un arbre en zone de cours et jardins2022

Other nearby cases : 19/PU/1846409, 19/SFD/1832464, 19/PU/1822752, 19/PU/1928687, 19/PU/2025969, 19/PU/1963758, 19/PU/1984456, 19/PU/1966920, 19/PU/2001084, 19/PFD/1810382, 19/PU/1916165, 19/PFD/1923164, 19/PU/1827146, 18/PU/1947796, 18/AA/2016233, 19/PFD/1811503, 19/PU/1908126