Rue de l'Urbanisme 52
Ganshoren · AA/492540 · Abattage d'arbres
Rue de l'Urbanisme 52, Ganshoren: tree felling. Case octroyé, lodged on 30 September 2013. The decision was notified on 8 October 2013, 8 days after lodging.
het vellen van een boom| Permit type | Abattage d'arbres | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 30 September 2013 | date the file was received |
| Decision notified | 8 October 2013 | 8 days |
| Floor areas | — | not reported by the source |
| Competent authority | Ganshoren |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 6 m | Façade and windows | mise en conformité des menuiseries en façade avant | 2024 |
| 12 m | Extension or raising | agrandir le balcon en façade arrière | 2023 |
| 12 m | Roof | isoler les toitures et modifier la couleur des tuiles | 2024 |
| 12 m | Roof | isoler la toiture par l'extérieur et mettre en conformité la façade et ses menuiseries en plus de la fermeture d'une cou | 2025 |
| 27 m | Roof | mettre en conformité la façade avant et l'aménagement d'une terrasse sur le toit plat au 3ème étage de l'immeuble | 2024 |
Other nearby cases : 08/SFD/1959307, 08/PU/1994861, 08/PU/1944381, 08/PU/1978338, 08/PU/1860457, 08/PU/1864781, 08/PU/1899306, 08/PU/2000183, 08/PU/1823640, 08/PU/1899023, 08/PU/1829856, 08/PU/1863982, 08/PU/2028134, 08/PU/1853640, 08/PU/1924116, 03/PFD/2016754, 08/PU/1936235, 08/PU/1863281, 08/PU/1821213, 08/PU/1858460, 08/AA/1821194, 08/PU/1989805, 08/GOU_PU/2036352, 08/PU/2014455, 08/PFD/2024361
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)