Rue Malibran 87
Ixelles · C_PLP/636073 · Prolongation de PE Communal
Rue Malibran 87, Ixelles: operation of installations. Case octroyé, lodged on 20 April 2017. The decision was notified on 26 June 2017, 67 days after lodging.
prolongation du permis pour une boucherie et une installation de refroidissement| Permit type | Prolongation de PE Communal | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 20 April 2017 | date the file was received |
| Decision notified | 26 June 2017 | 67 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 7 m | Change of use | aménager un équipement médical à la place d'une partie du commerce au rez-de-chaussée (actuellement un studio en infract | 2022 |
| 31 m | Other | Délai défini à défaut d'analyse de la complétude (160 j) | 2022 |
| 32 m | Heavy renovation | régulariser les transformations structurelles intérieures, la modification des menuiseries en façade avant et l'isolatio | 2024 |
| 34 m | Other | organiser un événement lumière "Bright Brussels" du 10/02 au 13/02/2022. | 2021 |
| 43 m | Extension or raising | transformer et mettre en conformité l’immeuble notamment étendre et rehausse l’immeuble, aménager une terrasse au +2, mo | 2023 |
Other nearby cases : 09/PU/1829412, 09/PU/1844042, 09/SFD/1843709, 09/PU/1907596, 09/PU/1868107, 09/GOU_PU/1953725, 09/SFD/1832844, 09/PU/1908728, 09/PU/1937986, 09/PU/1947523, 09/PU/1841545, 09/PU/1984038, 09/GOU_PU/1894311, 09/PU/1868451, 09/PU/1994252, 09/PU/1831139, 09/PFD/1933468, 09/PFD/1992501, 09/SFD/1834001, 09/PU/1820848, 09/PU/1979761, 09/PU/1799680, 09/SFD/1829658, 09/PFD/1992300, 09/PU/2040356
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)