Skip to content
AltUrb
Granted

Boulevard Anspach 52–54

Bruxelles · C_PLP/670617 · Prolongation de PE Communal

Boulevard Anspach 52–54, Bruxelles: operation of installations. Case octroyé, lodged on 7 March 2018. The decision was notified on 25 May 2018, 79 days after lodging.

exploiter un lunapark
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typeProlongation de PE Communal
StatusOctroyé
Lodged on7 March 2018date the file was received
Decision notified25 May 201879 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared complete
  3. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
15 mSigns and advertisingplacer 6 enseignes, 2 enseignes perpendiculaires, 2 enseignes parallèles et 2 stickers au-dessus des entrées2023
31 mFaçade and windowsmodifier la façade du rez-de-chaussée (régularisation)2024
38 mRetail or horeca fit-outAménager un bar dénommé ‘Le Scène Bar’ et rajouter 5 chambres hôtelière à l’hôtel existant au 1er étage2023
38 mSigns and advertisingRégulariser l'enseigne parallèle : écran LED en imposte au-dessus de la porte d'entrée ; placer une nouvelle enseigne pe2024
38 mFaçade and windowspercer le mur de façade afin de créer une baie permettant d'avoir accès vers une nouvelle terrasse couverte2022

Other nearby cases : 04/PFU/1852381, 04/PFU/1856779, 04/PU/1866559, 04/PFU/1902898, 04/PU/2023520, 04/PU/1866590, 04/PU/1965276, 04/PU/1995330, 04/PU/1959917, 04/PU/1899353, 04/PU/1823184, 04/PU/1820823, 04/SFD/1857171, 04/SFD/1836033, 04/PU/1932266, 04/PU/1918332, 04/PU/1946965, 04/PFD/1975683, 04/PU/1975750, 04/PU/2033661, 04/PU/1830105, 04/SFD/1983766, 04/PU/1856927, 04/PU/1832074, 04/PU/1923490