Skip to content
AltUrb
Granted

Avenue Antoon van Oss 1

Bruxelles · CL2/627662 · Permis d'environnement communal Classe 2

Avenue Antoon van Oss 1, Bruxelles: operation of installations. Case octroyé, lodged on 15 February 2017. The decision was notified on 19 July 2017, 154 days after lodging.

dépôt pièces métalliques
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'environnement communal Classe 2
StatusOctroyé
Lodged on15 February 2017date the file was received
Public inquiry7 June 2017 – 22 June 2017
Decision notified19 July 2017154 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Public inquiry opened
  5. Public inquiry closed
  6. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
103 mChange of usechanger l'affectation d'une salle de réunion en un commerce de type Horeca (sandwicherie) au rez-de-chaussée d'un bâtime2023
109 mExtension or raisingd’une part, réaménager un centre de données, modifier les façades, rehausser le local technique, agrandir l’abri à vélos2025
109 mTree fellingabattre 30 arbres à haute tige en vue de construire un datacenter (permis A387/2019 et A536/2020)2024
116 mSigns and advertisingrenouveler un dispositif de publicité lumineuse double face2026
175 mNew constructionconstruire 2 cabines haute tension sur un dépôt de bus et abattre un arbre2023

Other nearby cases : 04/SFD/1924658, 04/PFD/1824404

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)