Rue du Duc 28
Woluwe-Saint-Pierre · CL3/455793 · Déclaration préalable Communal
Rue du Duc 28, Woluwe-Saint-Pierre: operation of installations. Case octroyé, lodged on 14 October 2009.
Exploitation d'un transformateur statique de 400 kVA| Permit type | Déclaration préalable Communal | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 14 October 2009 | date the file was received |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 51 m | Extension or raising | étendre et transformer une habitation unifamiliale mitoyenne | 2023 |
| 55 m | Façade and windows | Isoler un pignon mitoyen d'un immeuble à appartements | 2022 |
| 55 m | Façade and windows | Isolation d'un pignon mitoyen d'un immeuble à appartements | 2021 |
| 55 m | Façade and windows | isolation d'un pignon mitoyen | 2022 |
| 57 m | Façade and windows | remplacement de la porte cochère de l'immeuble | 2024 |
Other nearby cases : 19/PU/1922422, 19/PU/1844130, 19/PU/1917386, 19/PU/1942243, 19/PU/1850231, 19/AA/1930261, 19/PU/1871441, 19/SFD/1834236, 19/PU/1850036, 19/PU/1945842, 19/PU/1826736, 19/PU/2041006, 19/PU/1850979, 19/PU/1910986, 19/PU/1833672, 19/PU/2001800, 19/PU/1909615, 19/PU/1831156, 19/GOU_PU/2009560, 19/PU/1869665, 19/PU/2025023, 19/PU/2041426, 19/PU/1967603, 18/PU/1948158, 18/PU/1958663
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)