Avenue Houba de Strooper 242
Bruxelles · CL3/586085 · Déclaration préalable Communal
Avenue Houba de Strooper 242, Bruxelles: operation of installations. Case octroyé, lodged on 24 November 2015.
Installation de combustion| Permit type | Déclaration préalable Communal | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 24 November 2015 | date the file was received |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared complete
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 30 m | Tree felling | abattre 3 arbres | 2024 |
| 37 m | Split into dwellings | transformer une maison unifamiliale en 2 duplex (2 x 3 ch.); modifier le volume de l'annexe au RDC ; remplacer la toitur | 2022 |
| 86 m | Façade and windows | isoler la façade latérale d'une maison unifamiliale | 2023 |
| 110 m | Extension or raising | baisser le niveau du jardin d'un étage, construire un escalier extérieur en façade arrière au niveau du rez-de-chaussée, | 2024 |
| 114 m | Split into dwellings | modifier le nombre et la répartition des logements de 2 à 3 logements (1 x 2 ch, 1 x 1 ch et 1 studio), étendre le nivea | 2023 |
Other nearby cases : 04/PU/1851462, 04/PU/1831551, 04/PU/2022566, 04/PU/1829709, 04/PU/2009228, 04/PU/1916001, 04/PU/1868431, 04/PU/1971454, 04/PFU/1921915, 04/PFU/1926551, 04/PFU/1953334, 04/PU/1917353, 04/PFU/2021134, 04/PFU/2008835, 04/PFD/1849399, 04/PU/1986895, 04/PU/1935588, 04/PFD/2016947, 04/PFD/1892485, 04/PU/1863945, 04/PU/2007257, 04/PU/1970994, 04/PU/1899147, 04/PU/1938365, 04/GOU_PU/2009610
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)