Chaussée de Helmet 198–200, Schaerbeek: operation of installations. Case octroyé, lodged on 7 August 2018.
exploiter une climatisation dans un bureau de poste| Permit type | Déclaration préalable Communal | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 7 August 2018 | date the file was received |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 10 m | Extension or raising | dans un bâtiment à usage mixte (un commerce et 2 logements),mettre en conformité la construction d’une annexe au rez-de | 2026 |
| 13 m | Tree felling | abattre un arbre à haute tige (érable sycomore) dans le jardin | 2026 |
| 24 m | Change of use | CLASSE SANS SUITE : dans un bâtiment comprenant deux commerces et 6 logements, changer l'utilisation d'un rez-de-chaussé | 2022 |
| 24 m | Façade and windows | Régulariser et mettre en conformité des modifications apportées à la façade avant, dans un immeuble à usage mixte (deux | 2025 |
| 24 m | Change of use | REALISE- dans un bâtiment à usage mixte (deux commerces et six logements), régulariser la construction d'une annexe au n | 2023 |
Other nearby cases : 15/PU/1871836, 15/AA/1835054, 15/PU/2024288, 15/PU/1800066, 15/PU/1835349, 15/PU/1894113, 15/PU/1955886, 15/PU/1976554, 15/PU/1831409, 15/PU/1967215, 15/ENS/1858836, 15/PU/1851654, 15/ENS/1901827, 15/PU/1901832, 15/PU/1971056, 15/PU/1894180, 15/PU/1935494, 15/PU/1821562, 15/PFD/1991627, 15/PU/1821268, 15/PU/1912640, 15/PU/1992713, 15/PU/1837134, 15/PU/1908446, 15/PU/1861109