Granted
Avenue du Port
Molenbeek-Saint-Jean · CU/207991 · Certificat d'urbanisme privé
Avenue du Port, Molenbeek-Saint-Jean: new construction. Case octroyé, lodged on 29 April 1996. The decision was notified on 4 October 1996, 158 days after lodging.
édicule d'entrée| Permit type | Certificat d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 29 April 1996 | date the file was received |
| Consultation committee | 14 May 1996 | |
| Decision notified | 4 October 1996 | 158 days |
| Floor areas | — | not reported by the source |
| Competent authority | Molenbeek-Saint-Jean |
Timeline
- Application lodged
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)