Granted
Rue Walcourt
Anderlecht · CU/333044 · Certificat d'urbanisme privé
Rue Walcourt, Anderlecht: new construction. Case octroyé, lodged on 24 July 2001. The decision was notified on 16 September 2002, 419 days after lodging.
construction de 5 immeubles de bureaux - nouvelle exploitation| Permit type | Certificat d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 24 July 2001 | date the file was received |
| Public inquiry | 31 August 2001 – 15 September 2001 | |
| Consultation committee | 10 October 2001 | |
| Decision notified | 16 September 2002 | 419 days |
| Floor areas | — | not reported by the source |
| Competent authority | Anderlecht |
Timeline
- Application lodged
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.