Chaussée de Haecht 708
Schaerbeek · PU/194972 · Permis d'urbanisme privé
Chaussée de Haecht 708, Schaerbeek: split into dwellings. Case octroyé, lodged on 16 November 2004. The decision was notified on 13 September 2005, 301 days after lodging. It comprises 1 dwellings.
Aménager +1 logement +3 et construire lucarne façade avant| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 16 November 2004 | date the file was received |
| Public inquiry | 28 February 2005 – 15 March 2005 | |
| Consultation committee | 15 April 2005 | |
| Decision notified | 13 September 2005 | 301 days |
| Floor areas | — | not reported by the source |
| Competent authority | Schaerbeek |
Timeline
- Application lodged
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 8 m | Extension or raising | dans une maison unifamiliale, mettre en conformité la modification de la toiture en façade arrière, la construction d'un | 2021 |
| 34 m | Extension or raising | dans une maison unifamiliale, régulariser la construction d'une annexe au premier étage, l'aménagement de deux logements | 2025 |
| 40 m | Extension or raising | REALISE- dans un immeuble de trois logements, régulariser la construction d'un étage supplémentaire et la construction d | 2023 |
| 40 m | Extension or raising | REFUS - dans un immeuble de 3 logements, régulariser la construction d'un étage supplémentaire et d'annexes à tous les é | 2021 |
| 40 m | Extension or raising | dans un immeuble de 3 logements, régulariser la construction d'un étage supplémentaire et d'annexes à tous les étages en | 2023 |
Other nearby cases : 15/PU/1914522, 15/PU/1986918, 15/PU/1860336, 15/PU/1831434, 15/PU/2039616, 15/PU/1835786, 15/PU/2006696, 15/PU/1948374, 15/ENS/1848775, 15/PU/1948287, 15/PU/1848772, 15/PU/1941322, 15/PU/1958176, 15/PU/1986167, 15/PU/2012583, 15/PU/2026135, 15/PU/1865887, 15/PU/1925635, 15/PU/2022210, 06/PFD/1836728, 15/PU/1944710, 15/PU/1835298, 15/PU/1869767, 06/PFD/1972503, 15/PU/1968612
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)