Avenue Emile Max 169
Schaerbeek · PU/196093 · Permis d'urbanisme privé
Avenue Emile Max 169, Schaerbeek: heavy renovation. Case octroyé, lodged on 4 October 2007. The decision was notified on 9 April 2008, 188 days after lodging.
Percer baies de porte entre immeuble mitoyen (+3)| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 4 October 2007 | date the file was received |
| Decision notified | 9 April 2008 | 188 days |
| Floor areas | — | not reported by the source |
| Competent authority | Schaerbeek |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 4 m | Change of use | dans un immeuble à usage mixte (un bureau et cinq logements), mettre en conformité le changement d’affectation du rez-de | 2023 |
| 43 m | Tree felling | Abattre un cerisier du Japon dans le jardin | 2023 |
| 43 m | Demolition and reconstruction | dans un bâtiment à usage mixte (bureau et logement), démolir et reconstruire les annexes arrière (rez-de-chaussée et 1er | 2024 |
| 52 m | Tree felling | abattre 8 arbres à haute-tige (acer pseudoplatanus) | 2022 |
| 58 m | Merger of dwellings | dans immeuble de 17 logements, réunir les deux appartements du 8ème étage (passe de 17 à 16 unités) en un seul logement, | 2022 |
Other nearby cases : 15/PU/1942645, 15/PU/1938685, 15/GOU_PU/2016923, 15/PU/1823176, 15/PU/1948056, 15/PU/2007484, 15/PU/1831755, 15/PU/1956144, 15/PU/2001249, 15/PU/1842596, 15/PU/1948515, 15/PFD/1839308, 15/PU/1844308, 15/PU/1938375, 15/PU/1930319, 15/PU/1917284, 15/GOU_PU/1968733, 15/PU/1910024, 15/PU/1846961, 15/PU/1829908, 15/PU/1941917, 15/PU/1832853, 15/PU/2001072, 15/PFD/2001781, 15/PU/1963861
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)