Avenue Milcamps 106
Schaerbeek · PU/196129 · Permis d'urbanisme privé
Avenue Milcamps 106, Schaerbeek: heavy renovation. Case octroyé, lodged on 7 November 2007. The decision was notified on 17 October 2008, 345 days after lodging.
Démolir des murs porteurs, aménager une terrasse et modifier la volumétrie d'un cabanon technique| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 7 November 2007 | date the file was received |
| Public inquiry | 13 December 2007 – 28 December 2007 | |
| Consultation committee | 11 January 2008 | |
| Decision notified | 17 October 2008 | 345 days |
| Floor areas | — | not reported by the source |
| Competent authority | Schaerbeek |
Timeline
- Application lodged
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 36 m | Extension or raising | dans une maison unifamiliale, construire un étage supplémentaire (R+3), réaménager les espaces intérieurs et apporter de | 2023 |
| 49 m | Extension or raising | dans un bâtiment comprenant 4 logements, mettre en conformité la fermeture d'un balcon au 3ième étage et l'aménagement d | 2026 |
| 51 m | Façade and windows | [CADUC] dans un immeuble comprenant 5 logements, placer un enduit sur isolent en façade arrière | 2024 |
| 54 m | Split into dwellings | REFUSE - dans un immeuble comprenant trois logements, mettre en conformité l’ajout d’un logement dans les combles, réali | 2023 |
| 58 m | Change of use | dans un immeuble à usage mixte (activité de production de biens immatériels et neuf logements), mettre en conformité l’e | 2025 |
Other nearby cases : 15/PU/2035761, 15/PU/1970073, 15/PU/1971318, 15/PU/1972153, 15/PU/1938088, 15/PU/2017538, 15/PU/1993203, 15/GOU_PU/1939582, 15/PU/1895285, 15/PFD/1820795, 15/PU/2002379, 15/PFD/1944408, 15/PU/1963129, 15/ENS/1892449, 15/PU/1982645, 15/PU/1961091, 15/PU/2017729, 15/PFD/1996112, 15/PFD/1863445, 15/PU/1800693, 15/GOU_PU/1901415, 15/PU/2018810, 15/PU/1869320, 15/PU/1830903, 15/PU/1827312
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)